• The plant has 58,38 MWe rated power with 6 sets of Wartsila 20V34SG Genset. Single Wartsila 20V34SG gas engine can produce 9,73 MWe electricity per hour. The mechanical power produced with 20 pistons, then transmitted to generator with the shaft and the 12163 kVA AVK Generators produce electricity and transmits to ABB MVCells via power cables.

• 90 MVA step up transformer located in 154 kV Switchyard, transmits the energy to the the electricity transmission line, which connects with Tire Substation about 2,5 km away from the site. Then the energy is transmitted to TEİAŞ (Turkish Electricity Transmission Company) main grid lines.